Roof Stripping |
The roof was stripped of all remaining shingles, staples were removed as well as all felt paper |
|
|
|
|
|
|
|
Roof Panels Inspection |
Each roof panel was inspected for damage from water or rot |
|
|
|
|
|
|
|
Roof Rot |
Two existing panels had signs of rot from moisture buildup |
|
|
|
|
|
|
|
Panel Removal |
Any damaged panels were removed |
|
|
|
|
|
|
|
New Panels |
10 new 4' x 8' x 1/2" approved panels were installed where deemed necessary |
|
|
|
|
|
|
|
Interior Inspection |
The interior of the roof was inspected to assure all water damaged panels were changed and no mold was evident |
|
|
|
|
|
|
|
Roof Cleanup |
Panels were re - nailed for added security and prepared for putting on felt |
|
|
|
|
|
|
|
Felt Rollout |
New #30 weight approved felt paper rolls were rolled out with an overhang of 19" on first row and 6" on each subsequent row |
|
|
|
|
|
|
|
Felt Application |
After rollout and inspection nail down begins |
|
|
|
|
|
|
|
Tin Tab Application |
Approved 1 5/8" Tin Tabs are affixed using 1 1/2" roofing nails applied by a pneumatic roofing nail gun. Each Tab is placed 1 foot from the next in rows 1 foot apart. |
|
|
|
|
|
|
|
Roofing Cement |
Approved roofing cement is applied where felt is interrupted |
|
|
|
|
|
|
|
Skylight Sealing |
Each skylight is sealed with roofing cement |
|
|
|
|
|
|
|
Breather Pipe Sealing |
Each 2" brether pipes from kitchen and bathroom plumbing below is sealed with roof cement |
|
|
|
|
|
|
|
Air Vent Sealing |
The air vent for the kitchen exhaust is sealed with roof cement |
|
|
|
|
|
|
|
Felt Inspection |
After nail-off, roof is checked to be sure felt is properly fixed |
|
|
|
|
|
|
|
Felt nail-off |
Every tab is checked and re-checked |
|
|
|
|
|
|
|
Felt completion |
Felt application is completed |
|
|
|
|
|
|
|
Felt Nail-off Inspection |
Once felt is down, a County Building Inspector will check for compliance with codes and permit on file |
|
|
|
|
|
|
|
Felt Inspection |
Dry-in inspection assures proper tin tab separation and felt application |
|
|
|
|
|
|
|
Roof Vent |
Following inspection, the roof cap vent is cut out |
|
|
|
|
|
|
|
Roof vent interior view |
The ridge vent runs entire length of roof and assures captive heat can vent adequately |
|
|
|
|
|
|
|
Ridge Vent Screen |
A wire screen 9" wide is affixed by staple gun to the ridge vent to keep insects out of the attic area |
|
|
|
|
|
|
|
Ridge Vent Screen |
The screen covers the entire ridge vent |
|
|
|
|
|
|
|
Ridge Vent completion |
Once the screen has been fully unrolled and stapled to the roof, the metal roof panels can be installed |
|
|
|
|
|
|
|
26 Guage Metalum Master Rib Panels |
Each panel is precut to fit each eave of the roof. The holes for the screws are predrilled before lifting them to the roof |
|
|
|
|
|
|
|
Roof Screws |
The screws are 1 1/2" long with a special neopreme washer. They are pre painted to match the roof panel colors. If the metal panels are being mounted over an existing asphalt shingled surface, the screws are 2" long |
|
|
|
|
|
|
|
Metal Sheet Mounting |
Each panel measures 43" wide and is mounted over the adjoining one. Actual surface coverage for each panel is 36" |
|
|
|
|
|
|
|
Final Inspection |
Once all the metal sheets are mounted and properly fastened, the County Building Inspector examines the completed work and approves the work and the Permit is finalized |
|
|
|
|
|
|